Ahwaz-Bangestan Technical Services for Oil Field Development

 

This six-month-long project for technical services was entrusted to PPZ Co. by Petroiran Development Company (PEDCO) and started on the 24th of April, 2005. The main purpose of the project was to commence the development of Ahwaz-Bangestan Oil Field through:

·         Collection and duplication of all upstream information

·         Preparing scope of work and seismic operation schedule

·         Observation and inspection of existing processing facilities

·         Preparing work program and budget

·         Providing required documents—MDP for Ahwaz-Bangestan Oil Field, histogram, coordination procedure, HSE plan and Organization chart

·         Presenting executive schedule for technical services

Pars Petro Zagros Company played a very significant part as upstream consultant company in the preparation of MDP and execution of the development operation until October 2005.